Switch Over 6 of Manggarai Station

December 9 to December 10, 2022, the first day of Switch Over 6 Manggarai Station activities has been carried out. A little explanation about Switch Over 6 Manggarai, namely activating the Signaling System, Railroad, Overflow Electricity for the operation of the new lines III & IV, Activating the new Upstream and Scissor Crossing lines between Manggarai - Jatinegara and deactivating the Manggarai II line. Switch Over 6 Manggarai has an impact on changes to the existing Kyosan K5B signaling system at Manggarai Station, changes to the Monitor Screen display (Control Console) in PPKA and in OCC, Upper Flow Electricity, Railroads and Train Operation Patterns.

Switch Over 6 Manggarai does not change the pattern of passenger service due to the unavailability of passenger service facilities (Lifts and Escalators) on platforms III and IV. Switch Over 6 Manggarau this time lasts for 3 days.
Day 1 on 09 - 10 December 2022 at 22.00 - 04.00 WIB;
Day 2 on 10 - 11 December 2022 at 13.00 - 15.00 and 22.00 - 04.00 WIB;
Day 3 on 12 - 13 December 2022 at 22.00 - 04.00 WIB.

1. Day 1, 9 facing December 10 2022, using Window Time at 22.00 - 04.00 WIB route II to Jatinegara is closed. If there is a train from GMR to JNG it is diverted via line VII.
2. Day 2, December 10 2022 using Window Time from 13.00 to 15.00 WIB, line I Manggarai is closed, if there is a train from JNG to GMR it is diverted via lines III & IV (via money orders 15/25) and on 10 facing December 11 2022 using Window Time at 22.00 - 04.00 WIB Manggarai line I is closed, if there is a train from JNG to GMR it is diverted via lines III & IV (via money lines 15/25).
3. Day 3, 12 facing December 13, 2022 using Window Time at 22.00 - 04.00 WIB, line I Manggarai is closed, if there is a train from JNG to GMR diverted through lines III & IV (via money lines 15/25).

The impact of the Manggarai switch over 6 activity was the cancellation of 40 KRL trips on the night of the activity. Adjustment of the travel schedule starts at night at 22.00 WIB, this is done to ensure safety when switch over 6 takes place both for workers and the safety of commuterline trips that will pass.

As said by the Secretary of the Directorate General of Railways of the Ministry of Transportation, Zulmafendi, this switch over activity was carried out to arrange and condition the railway line so that the construction of Manggarai Station can be continued and on schedule. "The large number of railroad tracks that cross has caused the need for traffic arrangements to accommodate train trips at this station," said Zulmafendi during the Ngobras event at the Ministry of Transportation Building, Jakarta, Wednesday (25/5/2022). (sf).